Field season report 2015. North Greenland Eemian Ice drilling East Greenland Ice drilling Project (NEEM/EGRIP): Moving the entire NEEM camp from NEEM site to EGRIP site by overland traverse. Setting up EGRIP camp structures

Title Field season report 2015. North Greenland Eemian Ice drilling East Greenland Ice drilling Project (NEEM/EGRIP): Moving the entire NEEM camp from NEEM site to EGRIP site by overland traverse. Setting up EGRIP camp structures
Publication Type
Report
Year
2015
Author(s) Jørgen P Steffensen , Lars B Larsen, Dorthe Dahl‐Jensen
Pagination
1-69
Abstract

This report has been prepared by the NEEM/EGRIP logistics group. The purpose is to provide the NEEM Scientific Steering Committee with a final report on cleaning up the former NEEM camp and the new EGRIP Steering Committee, relevant authorities and the NEEM/EGRIP 2015 participants with documentation of the events of the field season. The report contains information on the activities leading up to the field season and activities on the ice sheet. The SITREPs and camp diaries are included.

Besides listing the facts, it is our hope that the report can relay some of the special experiences which were part of the multinational efforts on the ice sheet.

To complete the logistical tasks during this special year of traverse activity, a lot of good will, help and flexibility of planning was needed from the organizers and personnel of the National Science Foundation GRiT traverse, the CH2MHill/CPS Polar Field Services, the 109th TAG, NYANG. The NEEM/EGRIP crew wishes to express sincere appreciation of this assistance to the field effort. We also wish to express sincere gratitude to Pat Smith, Stan Wisneski, Robin Abbott, Eric Coplin, Audrey Mills, Earl Vaughn and all other CH2MHill/CPS staff for their assistance.

File
URL
Categories Field Logistics/Camps
Citation Jørgen P Steffensen , Lars B Larsen, Dorthe Dahl‐Jensen ( 2015 ) Field season report 2015. North Greenland Eemian Ice drilling East Greenland Ice drilling Project (NEEM/EGRIP): Moving the entire NEEM camp from NEEM site to EGRIP site by overland traverse. Setting up EGRIP camp structures. 1-69 .
Lead Author
Jørgen P Steffensen